Battersea Power Station under construction

Battersea Power Station -
Phase 2


Selected by Battersea Power Station Development Company as supplier of choice following our previous success in delivering large complex projects which include Retail, Prime Residential and Commercial office space.

JDZ were appointed as MEP Technical Managers for the Battersea Power Station Phase 2 development. The Phase 2 development comprises the redevelopment of the iconic main power station, and is the centre piece of this prestigious multi-phase development. Based in the client project offices providing MEP design and delivery technical oversight for the Development Manager Battersea Power Station Development Company and working closely with the key members of the design and Construction team Mace, WEA Architects, and CBDSP.

To fulfil this role JDZ are committed to providing a full time resource based in the project offices at the Battersea construction site.

The project involves the full refurbishment of the iconic Battersea Power Station, as Phase 2 of a multi-phase development on the site, comprising of;

  • 500,000ft2 of commercial office space to be taken by Apple as single tenants for their European headquarters
  • 253Nr prime residential apartments
  • 100+ high quality retail and food and beverage outlets
  • 1400 person capacity events space
  • Client: Battersea Power Station Development Company


    Contractor: Mace (CM)


    Project Value: Confidential


    MEP Value: £250M


    Completion: 2021